Event Date | Event Description |
Wednesday, March 28, 2018 | NOTICE OF ACCEPTANCE OF SEC. 8 & 9 - E-MAILED |
Wednesday, March 28, 2018 | REGISTERED AND RENEWED (FIRST RENEWAL - 10 YRS) |
Wednesday, March 28, 2018 | REGISTERED - SEC. 8 (10-YR) ACCEPTED/SEC. 9 GRANTED |
Wednesday, March 21, 2018 | TEAS RESPONSE TO OFFICE ACTION-POST REG RECEIVED |
Friday, March 9, 2018 | POST REGISTRATION ACTION MAILED - SEC. 8 & 9 |
Wednesday, February 14, 2018 | TEAS RESPONSE TO OFFICE ACTION-POST REG RECEIVED |
Tuesday, September 12, 2017 | POST REGISTRATION ACTION MAILED - SEC. 8 & 9 |
Tuesday, August 22, 2017 | CASE ASSIGNED TO POST REGISTRATION PARALEGAL |
Wednesday, July 12, 2017 | TEAS SECTION 8 & 9 RECEIVED |
Wednesday, July 12, 2017 | TEAS CHANGE OF CORRESPONDENCE RECEIVED |
Sunday, August 21, 2016 | COURTESY REMINDER - SEC. 8 (10-YR)/SEC. 9 E-MAILED |
Wednesday, July 24, 2013 | NOTICE OF ACCEPTANCE OF SEC. 8 & 15 - E-MAILED |
Wednesday, July 24, 2013 | REGISTERED - SEC. 8 (6-YR) ACCEPTED & SEC. 15 ACK. |
Wednesday, July 24, 2013 | CASE ASSIGNED TO POST REGISTRATION PARALEGAL |
Thursday, July 11, 2013 | TEAS SECTION 8 & 15 RECEIVED |
Thursday, July 11, 2013 | TEAS CHANGE OF CORRESPONDENCE RECEIVED |
Tuesday, August 21, 2007 | REGISTERED-PRINCIPAL REGISTER |
Monday, July 16, 2007 | LAW OFFICE REGISTRATION REVIEW COMPLETED |
Monday, July 16, 2007 | ALLOWED PRINCIPAL REGISTER - SOU ACCEPTED |
Wednesday, June 13, 2007 | TEAS/EMAIL CORRESPONDENCE ENTERED |
Wednesday, June 13, 2007 | CORRESPONDENCE RECEIVED IN LAW OFFICE |
Wednesday, June 13, 2007 | ASSIGNED TO LIE |
Tuesday, May 29, 2007 | TEAS RESPONSE TO OFFICE ACTION RECEIVED |
Monday, November 27, 2006 | NON-FINAL ACTION E-MAILED |
Monday, November 27, 2006 | SU - NON-FINAL ACTION - WRITTEN |
Monday, November 6, 2006 | STATEMENT OF USE PROCESSING COMPLETE |
Monday, November 6, 2006 | EXTENSION 3 GRANTED |
Wednesday, October 4, 2006 | USE AMENDMENT FILED |
Wednesday, October 4, 2006 | EXTENSION 3 FILED |
Wednesday, October 4, 2006 | TEAS EXTENSION RECEIVED |
Wednesday, October 4, 2006 | TEAS STATEMENT OF USE RECEIVED |
Tuesday, April 4, 2006 | EXTENSION 2 GRANTED |
Tuesday, April 4, 2006 | EXTENSION 2 FILED |
Tuesday, April 4, 2006 | TEAS EXTENSION RECEIVED |
Monday, October 3, 2005 | EXTENSION 1 GRANTED |
Monday, October 3, 2005 | EXTENSION 1 FILED |
Monday, October 3, 2005 | TEAS EXTENSION RECEIVED |
Tuesday, April 5, 2005 | NOA MAILED - SOU REQUIRED FROM APPLICANT |
Tuesday, January 11, 2005 | PUBLISHED FOR OPPOSITION |
Wednesday, December 22, 2004 | NOTICE OF PUBLICATION |
Thursday, November 4, 2004 | LAW OFFICE PUBLICATION REVIEW COMPLETED |
Friday, October 22, 2004 | ASSIGNED TO LIE |
Thursday, October 14, 2004 | APPROVED FOR PUB - PRINCIPAL REGISTER |
Thursday, September 30, 2004 | ASSIGNED TO EXAMINER |
Thursday, April 1, 2004 | NEW APPLICATION ENTERED IN TRAM |